Views: 0 Author: Site Editor Publish Time: 2026-11-23 Origin: Site
Extra thickness belongs where repeated, concentrated load lands in the same small footprint — sprint starts, relay change-over zones, the bends and jump approaches — and each needs a start limit, a stop limit and a joint detail back to the standard surface. The roll format, the base flatness and the joint decide whether a thickened zone behaves as designed.
A separate, thicker build-up is usually drawn where force lands in the same footprint again and again: sprint starts and the first metres of acceleration, relay change-over zones, the bends, and the approach and take-off areas of the jumps. Published supplier guidance names those high-impact areas and ties thickness to base flatness, drainage, installation quality and climate exposure.
Landing surrounds, aprons and maintenance routes stay in the schedule as separate line items: what crosses them differs from what crosses a lane, so agree their limits and build-up with the venue operator.
| Zone or area | Loading that justifies a separate thickness | What the drawing has to close |
|---|---|---|
| Sprint starts and the acceleration metres after them | Repeated block contact and drive forces in the same footprints; sprint starts are named as a high-impact area. | Start and stop limits, a build-up stated by layer, and one transition joint to the standard surface. |
| Relay change-over zones | Repeated outgoing and incoming foot contact inside a short marked length, named as a high-impact area. | The zone length measured on the running line, with the same build-up and joint detail as the start zone. |
| Bends, including blocks set in the curve | Combined vertical and lateral load during curve running and starting; curves are named among the high-impact areas. | Limits that follow the curve geometry, plus the curve laying treatment in the installation sequence. |
| Jump approaches and take-off areas | Concentrated take-off force at the board and repeated approach strides; jumping approaches are named in the same guidance. | The approach limit, the board zone, and the joint where the approach meets the lane or the infield. |
| Landing surrounds, aprons and maintenance routes | Mixed and site-specific: landing implements, trolleys, service vehicles and spectator movement. | A decision on whether the area takes the standard build-up or a heavier one, with its own limit and joint. |
| Base and drainage beneath every zone | The installation sequence inspects, grinds and seals the base and fills depressions for flatness before any roll is laid. | Base tolerance and drainage for each zone, and a note that thickness does not correct an uneven base. |
They are watched separately because one small area takes load repeatedly, and a surface too thin for its duty level may wear quickly there. The supplier's guidance names those areas as high-impact and sets out 9 mm, 13 mm and 15 mm-or-thicker tiers for light, school and high-use stadium duty.
Yes, keep them in one schedule, but not as one line item. Runways and jump approaches behave like the lanes they join; landing surrounds, aprons and service routes carry different traffic and need their own limits and build-up decision.
A thickened area is a closed shape, not a fade-out. Draw its start and stop limits on a straight, low-load line rather than mid-acceleration or mid-landing, give the zone its own build-up in section, and show one reusable transition detail back to the standard surface. Thickness cannot level an uneven base.
The GOTER prefabricated environmental rubber track is published in a fixed nominal format — 9–13 mm thick, 1.22 m wide and 15–20 m long — so local thickness cannot be ordered as one thick roll. It comes from the detailed build-up and transition, and from the base beneath.
The same nominal format is published for the GOMER and GODER models, both described as double-layer constructions with a 4 mm surface layer over a 9 mm bottom layer. If you are choosing a duty tier before you settle the zones, the supplier's guidance on how to choose the right running track thickness for schools and stadiums sets out the 9 mm, 13 mm and 15 mm-or-thicker tiers for light, school and high-use stadium duty, with the base, drainage, installation and climate factors that go with them.
| Approach | How it is achieved | Where it makes sense | What changes on the drawing and in the order |
|---|---|---|---|
| One higher tier across the whole track | Specify the higher duty tier everywhere instead of a separate zone build-up. | Venues with heavy, spread-out use that want one surface condition throughout. | A single build-up on every sheet, no transition joints, and more of the same roll format. |
| Standard surface with closed thickened zones | Keep the standard product and detail a thicker build-up only inside the marked zones. | Designs where load concentrates in a few footprints and the rest of the track carries normal use. | Two build-ups in the zone schedule, one reusable joint detail, and a base check under every zone. |
| Curve laying treatment | In the supplier's published installation method, the curve is brought down with thickened forming adhesive and pressure blocks. | Curved sections, whatever thickness tier is chosen. | Belongs in the method statement, not in the thickness schedule; it is not a surface-thickness increase. |
| Ordering one thick roll for a single zone | Not a standard option: the published roll format is a nominal 9–13 mm band, 1.22 m wide and 15–20 m long. | Not applicable. | Zone thickness has to come from the detailed build-up and joint, and the supplier should confirm in writing what it will supply. |
A complete thickened-zone package has four parts: a zone schedule with limits and build-ups by layer, a section detail showing the transition joint, a base and drainage requirement under every zone, and a facility-document reference with a handover check for each zone.
Walking the finished surface checks completed work; the installation crew carries out base preparation and laying under the project method statement.
Mark every area that takes repeated concentrated load as a closed zone with its own start limit, stop limit, build-up and joint, and keep the standard surface everywhere else.
Then check three things before the drawing goes out: the base under each zone is specified flat and drained rather than relied on for thickness, the roll format matches the thickness tier you have chosen, and every zone carries a written supplier confirmation and a handover check.
Short answers to the questions that come up most often when a locally thickened zone is added to a prefabricated track drawing.
It means a locally deeper build-up under a marked area, not a second surface laid on top. The published duty tiers describe overall use levels, and the same guidance notes that thickness is judged with base flatness, drainage, installation quality and climate exposure.
Curves are named among the high-impact areas, so a designer may thicken them, but no separate value for bends is published. In the supplier's published installation method, curves are brought down with thickened forming adhesive and pressure blocks, so confirm the curve treatment for the system you are specifying.
No. The installation sequence inspects, grinds and seals the base and fills depressions for flatness before any roll is laid, and the thickness guidance treats base flatness and drainage as separate conditions, so an uneven base has to be corrected in the base package.
No standard roll is published for a single zone. The prefabricated models come in a nominal 9–13 mm thickness band, 1.22 m wide and 15–20 m long, so local thickness comes from the detailed build-up and transition joint.
Name the facilities manual and the synthetic surface testing specification published by the sport's international governing body, and note that certified facilities and certified surfacing products sit on separate lists. Confirm which edition and which list apply to your venue.
The installation sequence includes a quality-control step that adjusts thickness and corrects defects, and handover includes a maintenance manual. Ask for that check to cover each thickened zone and its joint, with the record handed over.
The design team sets the requirement, the supplier confirms in writing what it will supply and how the joint is made, and the cost engineer prices the two build-ups separately. Agree it before the order, not on site.
No. The published double-layer models describe a 4 mm coloured surface layer over a 9 mm bottom layer inside a nominal 9–13 mm product, so say which layer changes when a zone is thickened.